Type of work

Industrial

Campeche electrical substation

Mexico

  • Campeche electrical substation
  • Campeche electrical substation
  • Campeche electrical substation
  • Campeche electrical substation
  • Campeche electrical substation
  • Campeche electrical substation
  • Campeche electrical substation
  • Campeche electrical substation
  • Campeche electrical substation
  • Campeche electrical substation

Description

Project 288 SLT 1722 DISTRIBUCION SUR (1 PHASE), consists of a “turnkey” (EPC) that consists of: GIS substation of 115 / 34.5, 13.8 kV, five bays and a capacity of 80 MVA and 4.8 MVAr of compensation, 16 Metalclad high voltage / medium voltage LAAT 115 kV cells and medium voltage distribution lines including the dismantling of the existing substation.

The work was carried out by modifying and replacing the existing electrical substation without loss of service at any time.
 

Responsible

This work will benefit more than 500.000 homes, enabling an improvement in energy efficiency.