Building Matías Hernández Collectors and Sub-Collectors

The works consisted of building collectors and sub-collectors for the sanitary sewage system, covering the districts of Panama and San Miguelito.

The project stretched approximately 20 km and the piping to be installed varied from having a 12" diameter, for the PVC pipes, to between 24" and 60" for the reinforced concrete pipes. Other activities connected to the system were also included: the construction of inspection chambers, connections to existing chambers, demolition and repositioning of the street surfacing (hydraulic and asphalt concrete), demolition and repositioning of structures (sidewalks, fences, walls, inverted arches, etc.).


Client: Ministry of Health

Start date: 18 June 2007

End date: 30 January 2013